Highway 36 & Lake Elmo Avenue Interchange Project
Location
- Intersection of Trunk Highway 36 and Lake Elmo Avenue (County State Aid Highway 17) located in the Cities of Grant and Lake Elmo.
Project Construction Schedule
- Early 2026 – Construction begins with relocation of private utility lines (phone, internet, natural gas, electric, etc.).
- Spring 2026 – Tree removals necessary for construction begins.
- Spring 2026 – Preconstruction Open House.
- Summer 2026 – Highway construction begins.
- Fall 2027 – Highway construction ends.
More details will be shared regarding construction staging, closures, detours, etc. at the preconstruction open house in the spring of 2026.
Recommended Alternative Project Layout (PDF)
Subscribe to Project Updates
Sign up for email alerts to be the first to know about project updates and other ways to be involved in the project by clicking on the button below.
Evaluation Process
Summary
A three-step process was used to evaluate intersection alternatives and select a preferred project alternative for the Highway 36 at Lake Elmo Avenue intersection. This process began with identifying a reasonable range of concepts. Each step of the process refined the alternatives through quantitative and qualitative analysis. Each step looked at the remaining alternatives at a progressively greater level of detail.
The outcome of Step 3 is the identification of a preferred alternative. The preferred alternative is now being advanced into final design and ultimately construction.
The three-step screening and evaluation process is described below:
Intersection Types Considered in Step 1 (PDF)
Step 1 Evaluation Results (PDF)
Alternatives Considered in Step 2 (PDF)
Step 2 Evaluation Results (PDF)
Alternatives Considered in Step 3 (PDF)
Step 3 Evaluation Results (PDF)
Open House #3 (January 10, 2024)
Open House #2 (April 19, 2023)
Purpose and Need (June 6, 2022)
Purpose and Need Postcard (PDF)
The draft Purpose and Need Document and draft Evaluation Criteria have been prepared as part of the environmental documentation phase of the project and will be used to help evaluate alternatives for improvements.
The information provided here is a summary of a longer technical report (PDF).
- Online Engagement
- Purpose and Need Public Comment Narrative Summary (PDF)
- Purpose and Need Public Comment One-Page Graphical Summary (PDF)
Open House #1 (November 9, 2021)
Goal Setting Workshop (October 13, 2021)
| DATE | ACTIVITY |
|---|---|
| 2021 - 2024 | Scoping and Preliminary Design |
| 2024 - 2025 | Final Design |
| 2026 - 2027 | Construction |
-
Andrew Giesen
Design EngineerPhone: 651-430-4336
-
Sharon Price
Right of Way SpecialistPhone: 651-430-4391